ORR METRO
AIRPORT METRO
MISC
Bid Award : November 2021
|
Work Commencement : February 2022
|
Revised Deadline : June 2027
Piers
96%
+1%
Normal Piers99%
Portal Piers88%
Caps/Beams
88%
+1%
Pier Caps97%
Portal Beams82%
Girders
87%
U Girder Spans95%
I-Girder Spans37%
Steel I Girder Spans50%
Steel U Girder Spans50%
HIGHLIGHTS:

  • 1st Steel U Girder launched.
  • Launching / Casting of all mainline Pier Caps completed.

JANUARY

2026

ISSUES:

  • Delay in launching Portal Beams at MAR i.e., AP1053, AP1054, AP1055, AP1056.
  • Delays in Viaduct completion between AP1035 to AP1057.

Progress In The Month
U Girders Progress In Last 6 Months
NOTE ON STATION'S PROGRESS:
    • ALL PUBLICLY TRACKABLE STATION'S PROGRESS ARE COMPLETED. REMAINING STATION WORK LIKE CONCOURSE SLAB, PLATFORM SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC CONTINUES. THESE WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    1st Steel U Girder Launched

    © Photo Copyright: Sunil
    Gallery Image 2

    At-Grade Slab Works Near Airport Station

    © Photo Copyright: Sunil
    Gallery Image 3

    Abutment At Doddajala Depot

    Video Of Progress As Of January 8th 2025: By Sunil