Casting of all Pier Caps of Jakkur Cross Station completed.
Roof truss erection work begins at Bagaluru Cross Station. 1st station with roof work in Airport Line.
1st UP Line pier cast between Kempapura & Hebbal.
OCTOBER
2025
ISSUES:
Delay in NHAI permission for barricading and traffic diversion to facilitate temporary support structure erection works to assemble OWG at Yelahanka
Dismantling of FOB pending near Bagalur Cross Station
No work happening at Hebbal Station since last 2 months.
Continuous changes in scope and delays in release of designs is delaying the project
Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTION
TOTAL
COMPLETED
COMPLETION
Piers GL To CL
16
16
CCL Beams
8
0
Pier CL To PD
16
0
PDL Beams
8
0
Pier PD To TL
16
0
PFL Beams
8
0
CCL RCC/I-Girders
71
0
DFL RCC/I-Girders
70
0
PFL RCC/I-Girders
50
0
U Girders
14
0
NOTE ON STATION'S PROGRESS TABLE:
STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.