Cumulative Progress
Piers
89% +2%
Caps + Beams + Tiebeams
74% +3%
Girders
61% +3%
Breakup
NORMAL PIERS
92%
PIER CAPS
77%
PORTAL PIERS
76%
PORTAL BEAMS
47%
U GIRDER SPANS
68%
I GIRDER SPANS
25%
STEEL GIRDER SPANS
22%
OWG
0%
HIGHLIGHTS:

  • 300th Pier Cap launched.
  • Casting of all Pier Caps of Jakkur Cross Station completed.
  • Roof truss erection work begins at Bagaluru Cross Station. 1st station with roof work in Airport Line.
  • 1st UP Line pier cast between Kempapura & Hebbal.

OCTOBER

2025

ISSUES:

  • Delay in NHAI permission for barricading and traffic diversion to facilitate temporary support structure erection works to assemble OWG at Yelahanka
  • Dismantling of FOB pending near Bagalur Cross Station
  • No work happening at Hebbal Station since last 2 months.
  • Continuous changes in scope and delays in release of designs is delaying the project

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
1616
CCL Beams
80
Pier CL To PD
160
PDL Beams
80
Pier PD To TL
160
PFL Beams
80
CCL RCC/I-Girders
710
DFL RCC/I-Girders
700
PFL RCC/I-Girders
500
U Girders
140
NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    Roof Work Begins At Bagaluru Cross Station

    © Photo Copyright: Sunil
    Gallery Image 2

    Stagnant Hebbal Station Works

    © Photo Copyright: Sunil
    Gallery Image 3

    UP & Down Line Near At Bagaluru Cross Station

    © Photo Copyright: Sunil
    Video Of Progress As Of November 6th 2025: By Sunil