ORR METRO
AIRPORT METRO
MISC
Bid Award : November 2021
|
Work Commencement : February 2022
|
Revised Deadline : December 2027
Piers
77%
+2%
Normal Piers90%
Portal Piers55%
Split Portal Piers79%
Caps/Beams
65%
+3%
Pier Caps77%
Portal Beams2%
Split Portal Tiebeams69%
Girders
37%
+3%
U Girder Spans43%
I-Girder Spans0%
Steel Girder Spans8%
HIGHLIGHTS:

  • 1st precast Portal Beam launched at Kasturinagara.
  • 1st Platform Pier Cap of Kasturinagara Station launched.
  • Launching of all Platform Pier Caps of Horamavu Station completed.
  • Launching of all U Girders of Kalyannagara Station completed.
  • 1st platform level I-Girder launched at Kalyannagara Station.
  • Veerannapalya Station: Casting of 1st pier upto track level completed.
  • Casting of all Podium Level Beams of Veerannapalya Station completed.
  • Launching of all girders of Kalyanagara Flyover completed.
  • AP14L piling commences which was held up due to pending land acquisition at Kasturinagara.

DECEMBER

2025

ISSUES:

  • No works happening at Nagawara Station since last 4 months. No works at Kempapura Station main grid too.
  • Delays in Pier works between HBR Layout Station to Veerannapalya. (AP226, AP227, AP229, AP236, AP237, AP238, AP239, AP256, AP258, AP259, AP267, AP271R, AP273R, AP274R, AP276L)
  • Delays in Pier works between Benniganahalli to Kasturinagara. (AP22-AP35)
  • Utility shifting pending at AP238R, near Nagawara Flyover.
  • Pace of work has severely slowed down at both Hennur Underpass split portal piers and Veerannapalya Flyover split portal piers. And as mentioned before, zero full pier completion at Nagawara flyover split portal piers.
  • Dependency on LG for a large portion of the alignment is going to slow down girder completion rate.
  • Continuous changes in scope and delays in release of designs is delaying the project.

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
88
CCL Pier Cap
88
Piers CL To TL
86
PFL Pier Cap
82
PFL Arms
160
CCL Arms
160
CCL RCC/I-Girder Spans
420
PFL RCC/I-Girder Spans
280
U Girders
140
NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    Veerannapalya Station

    © Photo Copyright: Sunil
    Gallery Image 2

    Work Commences At AP14L Post LA

    © Photo Copyright: Sunil
    Gallery Image 3

    All Girders Of Kalyannagara Flyover Completed

    © Photo Copyright: Sunil
    Video Of Progress As Of December 14th 2025: By Sunil