Bid Award : November 2021
|
Work Commencement : February 2022
|
Revised Deadline : December 2027
Piers
80%
+3%
Normal Piers90%
Portal Piers64%
Split Portal Piers80%
Caps/Beams
66%
+1%
Pier Caps77%
Portal Beams2%
Split Portal Tiebeams72%
Girders
38%
+1%
U Girder Spans45%
I-Girder Spans0%
Steel Girder Spans8%
HIGHLIGHTS:

  • Launching of all Station Arms of Horamavu Station completed.
  • Launching of I-Girders of Kalyan Nagara Station main grid completed.
  • 1st Platform Arm of Kasturinagara Station launched.
  • Casting of all piers of Kasturinagara Station upto track level completed.
  • Launching of Concourse Pier Caps of HBR Layout Station completed.
  • 1st pier of HBR Layout Station cast upto track level.

JANUARY

2026

ISSUES:

  • No works happening at Nagawara Station since last 4 months. No works at Kempapura Station main grid too.
  • Delays in Pier works between HBR Layout Station to Veerannapalya. (AP226, AP227, AP229, AP236, AP237, AP238, AP239, AP256, AP258, AP259, AP267, AP274R, AP276L).
  • Delays in Pier works between Benniganahalli to Kasturinagara. (AP22-AP35)
  • Utility shifting pending at AP238R, near Nagawara Flyover.
  • Pace of work is slow in completion of Split Portal Piers (Hennur Underpass, Veerannapalya Flyover, Nagawara Flyover).
  • Continuous changes in scope and delays in release of designs is delaying the project.

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
88
CCL Pier Cap
88
Piers CL To TL
88
PFL Pier Cap
85
PFL Arms
162
CCL Arms
160
CCL RCC/I-Girder Spans
420
PFL RCC/I-Girder Spans
280
U Girders
140
NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    HRBR Layout Station Entry/Exit Structure Works

    Gallery Image 2

    LG Being Dismantled At Babusapalya

    Gallery Image 3

    Veerannapalya Station

    Video Of Progress As Of January 11th 2025: By Sunil